Within scope
of the Kherrata Highway project under our commitment, the progress rate of
three (3) tunnels has reached 85%. In this project, which was suspended due to
the pandemic, works were relaunched in Lot 3 bis tunnels (3 tunnels) in April
2021, and the works were completed on August 4, 2021 as scheduled, and its
provisional acceptance was made. The progress rate of the works of Lot 2- Engineering
Structure is 80%, the necessary arrangements have been made for the completion
of the outstanding works to complete in 6 months, and the notification of the
work program has been made to all the authorities at the levels of the
Administration, the Governorate and the Ministry.